Reading: Akufo-Addo satisfied with work on Pokuase Interchange; Kwabenya-Taifa road
Share
Font ResizerAa
The News GodThe News God
Font ResizerAa
  • Politics
  • News
  • Business & Finance
  • Lifestyle & Health
  • Law
  • Sports
  • Tech & Autos
  • Home & Garden
  • Videos
  • More
Search
  • Politics
    • Trump
  • News
    • Wars & Conflicts
  • Business & Finance
  • Lifestyle & Health
  • Law
  • Sports
  • Tech & Autos
  • Home & Garden
  • Videos
  • More
    • Travel & Tour
    • Education
    • Entertainment
    • General
    • Pets
    • Blog
    • About Us
    • Disclaimer
    • Media Partners
    • Why You Need to Read Business News Everyday
    • Authors
    • Terms of Service & Privacy Policy
Follow US
  • About Us
  • Authors
  • Advertise
  • Contact Us
  • Disclaimer
  • My Bookmarks
  • Terms of Use & Privacy Policy
  • Media Partners
The News God > Blog > Politics > Akufo-Addo satisfied with work on Pokuase Interchange; Kwabenya-Taifa road
Politics

Akufo-Addo satisfied with work on Pokuase Interchange; Kwabenya-Taifa road

Sampson Gaddah
Last updated: December 3, 2019 11:19 am
Sampson Gaddah
December 3, 2019
Share
4 Min Read
Akufo-Addo satisfied with work on Pokuase Interchange; Kwabenya-Taifa road
SHARE

President Nana Addo Dankwa Akufo-Addo, on Monday, 2nd December 2019, expressed satisfaction with the progress of work currently taking place on the Pokuase Interchange.

With the project commencing in April 2018, and the interchange originally proposed as a 3-tier single-point urban interchange, the contractor, after undertaking a value engineering assessment, proposed to construct a 4-tier Stack Interchange, which was approved by the Ministry for Roads and Highways.

Thus far, road works, including drainage and pavement works, are far advanced, with most of the local roads identified for construction being concluded.

Additionally, some extra routes which became necessary after a review of the works are currently far advanced and will be completed before the end of 2019, with over 10 kilometres of local community roads being completed within the catchment area of the interchange.

Related Posts

Lindsey Graham, a Trump supporter, was booed off the stage at a South Carolina MAGA gathering near his home.
Schiff town hall erupts into clashes amid shouts of ‘liar’ and ‘treason’
President Yoon Impeached – South Korea’s Political Drama Unfolds
181 Factories enrolled under One District One Factory programme

Akufo-Addo satisfied with work on Pokuase Interchange; Kwabenya-Taifa road

The contractor, Zhongmei Engineering Group Ltd indicated that 4 kilometres of asphalt dual carriageway have been completed for the Awoshie section of the project, with landscaping, street lighting, road signs, pedestrian facilities currently underway.

Also, 1 kilometre of asphalt single carriageway has been completed for the Kwabenya section of the project, with pedestrian facilities, and retaining wall constructions being undertaken.

The supervising engineer on site told President Akufo-Addo that drainage works, retaining walls, earthworks are being constructed on the Accra to Kumasi road approaches to the interchange, in addition to the 2.8 kilometres of various sizes of outfall storm drains constructed as part of the project to date.

Touching on the interchange itself, the engineer revealed that 99% of pile foundation works have been completed. The progress to date for the various elements are as follows: 54% of all pile caps completed; 28% of Piers completed; 20% of Bridge Abutment completed; and 5% of Bridge Deck under construction.

He noted also that GRIDCo’s 330kv transmission line has been relocated, and 98% of ECG’s network, which was impacted by the project, has also been relocated. Also, about 400 metres of GWCL 300mm water mains have been relocated.

Dome Kwabenya

At Dome Kwabenya, President Akufo-Addo inspected work currently ongoing on the 5.5 kilometre Kwabenya Roundabout to Taifa Road.

This project was awarded in October 2017 to M/s. GHACOS Limited. The Contract sum is GH₵ 37,457,021.43 with funding from the Road Fund.

The scope of works involved the construction of 2.6 kilometres of road from the Kwabenya Roundabout to Taifa Nkatie Burger Junction; comprising of 1.6 kilometres of dual carriageway merging into a 1-kilometre single carriageway.

The construction also involves the construction of the 4.3-kilometre section of the Dome-Kitase Road with associated drainage works.

Thus far, the 2.6-kilometre road from Kwabenya Roundabout to Taifa Nkatei Burger junction is substantially completed with 300 metres of the 2.5m x 4.2m drain in place. The Construction of an outfall storm drain of size varying from 1.5m x 1.5m to 1.5m x 2.5m to logically discharge stormwater to the outfall is currently being constructed.

Additionally, the first 1.8 kilometres of the Dome-Kitase Road has been sealed, and the contractor is steadily constructing drains along the remaining stretch of the road.

The road is expected to be completed by June 2020.

 

 

 

Responding to Pelosi’s Communion ban, Durbin says “certain bishops’ conscience” cannot make such decisions.
Trump Impeachment: Readers Being Fooled by Media
Fox News Today: Sacramento State student appears to slap former College Republicans president on video
Is Joe Biden’s reelection a realistic possibility, in your opinion?
Fox News Today: Nancy Pelosi: ‘No question’ USMCA ‘much better than NAFTA’
Share This Article
Facebook Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article Mario Balotelli free to leave Brescia in January, says club's president Mario Balotelli free to leave Brescia in January, says club’s president
Next Article Two kids marry Wedding ceremony between two kids (PHOTOS)
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Latest Publications

Two women robbers dress as 'Roman' sisters to rob a bank
Two women robbers dress as ‘Roman’ sisters to rob a bank
News
May 30, 2025
7 Common Mistakes to Avoid When Beginning a Career in Education
Education
May 30, 2025
Home education
Why Continuing Education Matters More Than Ever in Healthcare
Education
May 29, 2025
26-year-old boy beaten up by 2 wives for trying to marry 3rd wife
26-year-old man beaten up by 2 wives for trying to marry 3rd wife
News
May 28, 2025
World’s longest-serving death row prisoner receives $1.4 million in compensation
World’s longest-serving death row prisoner receives $1.4 million in compensation
News
May 28, 2025

Stay Connected

235.3kFollowersLike
69.1kFollowersFollow
11.6kFollowersPin
56.4kFollowersFollow
136kSubscribersSubscribe

You Might also Like

Politics

President Biden believes Monkeypox should be a concern for “everyone.”

May 22, 2022
Politics

Rep. Sean Casten of Illinois shares new information concerning his daughter’s death: ‘It was tranquil.’

June 16, 2022
steyer,-sanders-spending-big-to-carpet-bomb-iowa-airwaves-in-final-caucus-stretch
Politics

Steyer, Sanders spending big to carpet-bomb Iowa airwaves in final caucus stretch

January 29, 2020
Donald Trump Plans to Reinstate Transgender Military Ban
Trump News

Donald Trump Plans to Reinstate Transgender Military Ban

November 29, 2024
Show More
© 2025 Thenewsgod. All Rights Reserved.
  • About
  • Contact Us
  • Terms of Use & Privacy Policy
  • Disclaimer
  • Authors
  • Media Partners
  • Videos
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?