Reading: Akufo-Addo satisfied with work on Pokuase Interchange; Kwabenya-Taifa road
Share
Font ResizerAa
The News GodThe News God
Font ResizerAa
  • Politics
  • News
  • Business & Finance
  • Lifestyle & Health
  • Law
  • Sports
  • Tech & Autos
  • Home & Garden
  • More
Search
  • Politics
    • Trump
  • News
    • Wars & Conflicts
  • Business & Finance
  • Lifestyle & Health
  • Law
  • Sports
  • Tech & Autos
  • Home & Garden
  • More
    • Travel & Tour
    • Education
    • Entertainment
    • General
    • Games
    • Pets
    • Blog
    • About Us
    • Disclaimer
    • Media Partners
    • Why You Need to Read Business News Everyday
    • Authors
    • Terms of Service & Privacy Policy
Follow US
  • About Us
  • Authors
  • Advertise
  • Contact Us
  • Disclaimer
  • My Bookmarks
  • Terms of Use & Privacy Policy
  • Media Partners
The News God > Blog > Politics > Akufo-Addo satisfied with work on Pokuase Interchange; Kwabenya-Taifa road
Politics

Akufo-Addo satisfied with work on Pokuase Interchange; Kwabenya-Taifa road

Sampson Gaddah
Last updated: December 3, 2019 11:19 am
Sampson Gaddah
December 3, 2019
Share
4 Min Read
Akufo-Addo satisfied with work on Pokuase Interchange; Kwabenya-Taifa road
SHARE

President Nana Addo Dankwa Akufo-Addo, on Monday, 2nd December 2019, expressed satisfaction with the progress of work currently taking place on the Pokuase Interchange.

With the project commencing in April 2018, and the interchange originally proposed as a 3-tier single-point urban interchange, the contractor, after undertaking a value engineering assessment, proposed to construct a 4-tier Stack Interchange, which was approved by the Ministry for Roads and Highways.

Thus far, road works, including drainage and pavement works, are far advanced, with most of the local roads identified for construction being concluded.

Additionally, some extra routes which became necessary after a review of the works are currently far advanced and will be completed before the end of 2019, with over 10 kilometres of local community roads being completed within the catchment area of the interchange.

Related Posts

EXCLUSIVE: Trump campaign marks biggest campaign fundraising month to date
EXCLUSIVE: Trump campaign marks biggest campaign fundraising month to date
Omar claim of PTSD ‘offensive’ to US veterans, Indiana congressman says; Squad member responds
Pelosi tours San Francisco’s Chinatown in attempt to ease fears of coronavirus
Trump’s Attempt to Derail Bipartisan Agreement Sparks Debate

Akufo-Addo satisfied with work on Pokuase Interchange; Kwabenya-Taifa road

The contractor, Zhongmei Engineering Group Ltd indicated that 4 kilometres of asphalt dual carriageway have been completed for the Awoshie section of the project, with landscaping, street lighting, road signs, pedestrian facilities currently underway.

Also, 1 kilometre of asphalt single carriageway has been completed for the Kwabenya section of the project, with pedestrian facilities, and retaining wall constructions being undertaken.

The supervising engineer on site told President Akufo-Addo that drainage works, retaining walls, earthworks are being constructed on the Accra to Kumasi road approaches to the interchange, in addition to the 2.8 kilometres of various sizes of outfall storm drains constructed as part of the project to date.

Touching on the interchange itself, the engineer revealed that 99% of pile foundation works have been completed. The progress to date for the various elements are as follows: 54% of all pile caps completed; 28% of Piers completed; 20% of Bridge Abutment completed; and 5% of Bridge Deck under construction.

He noted also that GRIDCo’s 330kv transmission line has been relocated, and 98% of ECG’s network, which was impacted by the project, has also been relocated. Also, about 400 metres of GWCL 300mm water mains have been relocated.

Dome Kwabenya

At Dome Kwabenya, President Akufo-Addo inspected work currently ongoing on the 5.5 kilometre Kwabenya Roundabout to Taifa Road.

This project was awarded in October 2017 to M/s. GHACOS Limited. The Contract sum is GH₵ 37,457,021.43 with funding from the Road Fund.

The scope of works involved the construction of 2.6 kilometres of road from the Kwabenya Roundabout to Taifa Nkatie Burger Junction; comprising of 1.6 kilometres of dual carriageway merging into a 1-kilometre single carriageway.

The construction also involves the construction of the 4.3-kilometre section of the Dome-Kitase Road with associated drainage works.

Thus far, the 2.6-kilometre road from Kwabenya Roundabout to Taifa Nkatei Burger junction is substantially completed with 300 metres of the 2.5m x 4.2m drain in place. The Construction of an outfall storm drain of size varying from 1.5m x 1.5m to 1.5m x 2.5m to logically discharge stormwater to the outfall is currently being constructed.

Additionally, the first 1.8 kilometres of the Dome-Kitase Road has been sealed, and the contractor is steadily constructing drains along the remaining stretch of the road.

The road is expected to be completed by June 2020.

 

 

 

Akufo-Addo leaving behind a legacy of corruption & confusion – MP
Biden’s message expressed his and the First Lady’s “prayers” for Buffalo victims and condemned hate crimes.
DONALD TRUMP TO IMPOSE 100% TARIFFS ON BRICS
South Florida shift helps DeSantis and Rubio cruise to victory
NC General Assembly to continue Medicaid expansion proposal
Share This Article
Facebook Email Print
Share
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Previous Article Mario Balotelli free to leave Brescia in January, says club's president Mario Balotelli free to leave Brescia in January, says club’s president
Next Article Two kids marry Wedding ceremony between two kids (PHOTOS)

Latest Publications

Minneapolis Catholic School Shooting
2 Children Killed, 20 Injured In Minneapolis Catholic School Shooting
News
August 27, 2025
Hamas probably wouldn’t have attacked if Trump were the president, says Benjamin Netanyahu
Hamas “probably” wouldn’t have attacked if Trump were the president, says Benjamin Netanyahu
News
August 27, 2025
Denmark summons top US officials
Denmark summons top US officials over suspected influence operations in Greenland
Politics
August 27, 2025
From Classic to Contemporary: 8 Most Entertaining Vampire Books Ever Written
Entertainment
August 27, 2025
New York Tour Bus Crash
At least 5 dead, Dozen Injured in New York Tour Bus Crash
News
August 26, 2025

Stay Connected

235.3kFollowersLike
69.1kFollowersFollow
11.6kFollowersPin
56.4kFollowersFollow
136kSubscribersSubscribe

You Might also Like

Politics

‘Messed up,’ say Americans in response to Biden’s management of the economy and his promotion of ‘Bidenomics’

July 10, 2023
Politics

Tim Scott defends his silent debate performance, claiming that “the loudest voices too often say too little.”

September 10, 2023
democratic-impeachment-managers-blast-mcconnell’s-trial-rules-as-‘rigged’
Politics

Democratic impeachment managers blast McConnell’s trial rules as ‘rigged’

January 21, 2020
Sen. Bernie Sanders told President Trump “we’re not delaying the election” after Trump on Thursday suggested doing so until people can “safely vote.”
Politics

‘we’re not delaying the election,’ ‘your disastrous presidency will end’ – Bernie Sanders Fires Trump

July 30, 2020
Show More
© 2025 Thenewsgod. All Rights Reserved.
  • About
  • Contact Us
  • Terms of Use & Privacy Policy
  • Disclaimer
  • Authors
  • Media Partners
  • Videos
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?